Construction of Mumbai-Pune Expressway, Kon to Kalamboli bypassing Panvel town Package-I.
- Length: 8.10 kms
- Configuration: 6 lane Expressway
- Project Cost: Rs. 90 Crs.
- Client: Maharashtra State Road Development Corporation Ltd., Mumbai
- Other Features if any: India’s first six-lane concrete, high-speed, access controlled expressway.
Four Laning of Satara - Kolhapur up to Maharashtra State Border, Section of NH-4, Package-II from Km 616/000 to Km 639/000.
- Length: 23 kms (includes 2 Flyovers & 2 Major River Bridges
- Configuration: 4 lane
- Project Cost: Rs. 112 Crs.
- Client: Maharashtra State Road Development Corporation Ltd., Mumbai
- Other Features if any: The project was part of Golden Quadrilateral Delhi – Kolkatta – Chennai – Mumbai
Independent Engineer for Construction of 8 laning of existing 4 lane Vadape to Thane from KM 539.202 to KM 563.000 section of NH-3 (New NH 848) under Bharatmala Pariyojna in the State of Maharashtra on Hybrid Annuity Mode.
- Length: 23.798 Km
- Configuration: 8 lane
- Project Cost: Rs.1200 Cr.
- Client: National Highways Authority of India
Construction of Pilot Corridor under BRTS on A. B road in Indore (Niranjanpur to Rajiv Gandhi Square) under JNNURM in the State of Madhya Pradesh.
- Length: 11.46 kms
- Configuration: 4 lane + service roads of 2 lanes on either side
- Project Cost: Rs. 137.70 Crs.
- Client: Indore Development Authority, Indore
- Other Features if any: It is the Bus Rapid Transit System for Indore city also called as i-Bus (Intelligent Bus)
Construction of Bypass Road for Mehkar Town including Bridge across Painganga River in the State of Maharashtra.
- Length: 7.50 kms (includes Major Bridge across Painganga river)
- Configuration: 2 lane
- Project Cost: Road Rs. 39.50 Crs.
- Client: MSRDC Ltd., Nagpur
Independent Engineer for Up-gradation of Road for World Famous Lonar Lake, SH-51 in Buldhana District (Deulgaon Raja - Sindkhed Raja - Dusarbid - Lonar to Buldhana District Border, Length 48.50 Km) in the State of Maharashtra on Hybrid Annuity Mode (Package No. AM-76).
- Length: 48.50 kms
- Configuration: 2 lane with paved shoulder / 4 lane
- Project Cost: Rs. 135.50 Crs.
- Client: PWD, Govt. of Maharashtra
- Other Features if any: The Project establishes the connection to Sindkhed Raja, the birth place of Rajmata Jijabai Bhosale and the World Famous Lonar Lake.
Independent Engineer for Improvement of
- Ring Road in Yavatmal District (Yavatmal Bypass, Length 14.72 Km.
- Yavatmal – Babhulgaon – Kalamb road, Length 34.23 Km in Yavatmal District in the State of Maharashtra on Hybrid Annuity Mode (Package No. AM-89 A&B).
OTHER PROJECTS
- Construction of Mumbai – Pune Expressway, Kon to Kalamboli bypassing Panvel town Package-I.
- Authority’s Engineer for Rehabilitation and Up-gradation to 2 lanes with paved shoulder / 4 lane standard of National Highways section Dahegaon – Kuhi section (Length 41.54 kms) of NH-247 in the State of Maharashtra on EPC mode.
- Independent Engineer for Improvement of Aatpadi to Salgare (SH-153), Km 65/503 to km 135/500 in Sangli District in the State of Maharashtra on Hybrid Annuity Basis (Package No. PN- 41).
- Independent Engineer for Improvement of Arwade to Dighanchi (SH-151), Km 63/000 to Km 127/950 in Sangli District in the State of Maharashtra on Hybrid Annuity Mode (Package No. PN-44).
- Independent Engineer for Improvement of
- (i) Safale – Manda -Tembhi – Khodave, Km 0/000 to Km 9/100
- (ii) Nandore – Mann – Kallole, Km 0/00 to Km 9/200
- (iii) Parnali – Palghar road Km 0/00 to Km 14/900
- (iv) Chinchani – Ashagad – Udhva, Km 0/00 to Km 34/500 in Palghar District in the State of Maharashtra on Hybrid Annuity Mode (Package No. MU-01).
- Independent Engineer for Improvement of
- (i) Shahapur – Shenwa – Dolkhamb – Chondha – Sangamner – Shegaon – Nanded – Dharmabad Road, SH-50, Km 0/000 to Km 38/000
- (ii) Kambare – Piwali – Washind Road, MDR-57, Km 0.00 to Km 23.600 in Thane District in the State of Maharashtra on Hybrid Annuity Mode (Package No. MU-04).
- Independent Engineer for Improvement of
- (i) Bhoyegaon – Gadchandur – Jiwati Road (Length 21 Km),
- (ii) Gadchandur – Patan – Wani Road (Length 53 Km) in Chandrapur District in the State of Maharashtra on Hybrid Annuity Mode (Package No. NAG-142).
- Independent Engineer for Improvement of Nagpur – Nagbhid – Mul Road, Km 97/200 to Km 156/200 in Chandrapur District in the State of Maharashtra on Hybrid Annuity Mode (Package No. NAG 144).
- Independent Engineer for Improvement of
- (i) Bari to Sangamner, Length 67.60 Km and
- (ii) Randhafall to Varanghushi, Length 16.230 Km in Ahmednagar District in the State of Maharashtra on Hybrid Annuity Mode (Package No. NSK-71).
- Improvement to Nagpur – Aurangabad – Sinner – Ghoti – Mumbai NH Standard Road. Section : Lasur to Vaijapur (Pkg – XIII).
- Improvement and Up-gradation of road network at Piligao, Curti, Ponda Town and Chodan in the State of Goa.
- Construction of Easterly Diversion Road Outside Nanded City from Km. 7/840 to Km 8/560 in the State of Maharashtra.